This project includes four subprojects:
A) Renovation and Development Project of Jackets and Conductors: It
includes detailed engineering, procurement, construction, and
installation of Jackets for five platforms. The platforms are P4
(Production) – Q4 (Control and living quarter) – W0-W4 (Drilling) –
F4 (Flare) and this project also includes conductor pipes of
production wells W0 and W4.
B) Renovation and Development Project of Topside
& Bridges: It includes detailed engineering, procurement,
construction, installation and commissioning of topsides for five
platforms named P4 (Production) – Q4 (Control and living quarter) –
W0-W4 (Drilling) – F4 (Flare) as well as their bridges.
C) Pipelines and Sub Sea Cables Project: It
includes detailed engineering, procurement, construction,
installation and commissioning of the pipelines and sub sea cables
for the platforms of Reshadat field.
D) Drilling Project: It includes designing and
drilling of 16 production wells and 12 injection wells in Reshadat
field.
|