This project includes three subprojects:
A) Sub Sea Pipe laying Project: Laying about 200
Kilometres of 8", 12", 14", 16" and 26" diameters pipelines for
transferring the produced associated gas from their offshore
platforms to Kharg Island.
Estimated duration of this project is 28 months.
B) Offshore Platforms Modification Project:
Construction of two Gas compression platforms close to Bahregansar
and Aboozar production platforms.
Estimated duration of this project is 38 months.
C) Onshore Natural Gas Liquid Recovery Plant in
Kharg Island: Gas gathering and liquidated gas separation facilities
of NGL Plant, storage tanks, export jetty and other dependent
facilities.
Estimated duration of this project is 44 months.
The products of this project will be dry Methane
and Ethane gases as well as liquidated gasses like Propane, Butane,
Pentane and Naphtha. Based on the above production forecasts and the
internal rate of return of this project, its total income will reach
to $719 Million USD per year.
|